| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 1 | Project Management Plan | 49 days | Thu 4/1/04 | Tue 6/8/04 | | 0% |
| 2 | Initiating | 2 days | Thu 4/1/04 | Fri 4/2/04 | | 0% |
| 3 | Project Initiation | 2 days | Thu 4/1/04 | Fri 4/2/04 | | 0% |
| 4 | Identify goals and objectives | 1 day | Thu 4/1/04 | Thu 4/1/04 | Project Director | 0% |
| 5 | Document project costs and benefits | 0.5 days | Fri 4/2/04 | Fri 4/2/04 | Application Architect,Project Manager,Technical Architect | 0% |
| 6 | Develop project charter | 0.5 days | Fri 4/2/04 | Fri 4/2/04 | Project Manager,Acceptor | 0% |
| 7 | Planning | 21 days | Mon 4/5/04 | Mon 5/3/04 | | 0% |
| 8 | Define Scope | 6.5 days | Mon 4/5/04 | Tue 4/13/04 | | 0% |
| 9 | Develop strategies and plans | 1 day | Mon 4/5/04 | Mon 4/5/04 | Project Director | 0% |
| 10 | Conduct planning workshop | 1 day | Tue 4/6/04 | Tue 4/6/04 | Project Director | 0% |
| 11 | Research previous experience | 1 day | Mon 4/5/04 | Mon 4/5/04 | Project Manager | 0% |
| 12 | Define scope | 1 day | Wed 4/7/04 | Wed 4/7/04 | Project Manager | 0% |
| 13 | Develop high-level work breakdown structure | 1 day | Thu 4/8/04 | Thu 4/8/04 | Project Manager | 0% |
| 14 | Build detailed work breakdown structure | 1 day | Fri 4/9/04 | Fri 4/9/04 | Project Manager | 0% |
| 15 | Document project costs and benefits | 0.5 days | Tue 4/13/04 | Tue 4/13/04 | Application Architect,Project Manager,Technical Architect | 0% |
| 16 | Specify deliverables and acceptance criteria | 1 day | Mon 4/12/04 | Mon 4/12/04 | Project Manager | 0% |
| 17 | Document assumptions | 1 day | Mon 4/12/04 | Tue 4/13/04 | Project Manager | 0% |
| 18 | Document Project Support Plans | 0.5 days | Mon 4/26/04 | Mon 4/26/04 | | 0% |
| 19 | Document risk management plan | 0.5 days | Mon 4/26/04 | Mon 4/26/04 | Project Manager,Acceptor | 0% |
| 20 | Document configuration management plan | 0.5 days | Mon 4/26/04 | Mon 4/26/04 | Project Manager,Acceptor | 0% |
| 21 | Document data management plan | 0.5 days | Mon 4/26/04 | Mon 4/26/04 | Project Manager,Acceptor | 0% |
| 22 | Document communications management plan | 0.5 days | Mon 4/26/04 | Mon 4/26/04 | Project Manager,Acceptor | 0% |
| 23 | Develop Project Schedule | 5.5 days | Tue 4/13/04 | Tue 4/20/04 | | 0% |
| 24 | Develop resource plans | 1 day | Tue 4/13/04 | Wed 4/14/04 | Project Manager | 0% |
| 25 | Prepare project estimates | 1 day | Fri 4/16/04 | Mon 4/19/04 | Project Manager | 0% |
| 26 | Define dependencies and develop project schedule | 1 day | Mon 4/19/04 | Mon 4/19/04 | Project Manager | 0% |
| 27 | Document assumptions | 1 day | Mon 4/19/04 | Mon 4/19/04 | Project Manager | 0% |
| 28 | Conduct peer review | 1 day | Tue 4/20/04 | Tue 4/20/04 | Project Manager | 0% |
| 29 | Develop Financial Plan | 2 days | Mon 4/26/04 | Tue 4/27/04 | | 0% |
| 30 | Prepare financial plan | 1 day | Mon 4/26/04 | Mon 4/26/04 | Project Director | 0% |
| 31 | Set up standards and procedures for cost and schedule management | 1 day | Tue 4/27/04 | Tue 4/27/04 | Project Director | 0% |
| 32 | Plan for Quality | 2.5 days | Tue 4/13/04 | Thu 4/15/04 | | 0% |
| 33 | Define quality requirements | 1 day | Tue 4/13/04 | Wed 4/14/04 | Quality Assurance Manager | 0% |
| 34 | Set up standards and procedures for quality management | 1 day | Wed 4/14/04 | Thu 4/15/04 | Quality Assurance Manager | 0% |
| 35 | Document quality management plan | 0.5 days | Thu 4/15/04 | Thu 4/15/04 | Quality Assurance Manager,Acceptor | 0% |
| 36 | Develop Risk Plans | 2.5 days | Tue 4/20/04 | Thu 4/22/04 | | 0% |
| 37 | Identify risks | 1 day | Tue 4/20/04 | Wed 4/21/04 | Project Manager | 0% |
| 38 | Analyze risks | 1 day | Wed 4/21/04 | Thu 4/22/04 | Project Manager | 0% |
| 39 | Document risks | 0.5 days | Thu 4/22/04 | Thu 4/22/04 | Project Manager,Acceptor | 0% |
| 40 | Organize Project Resources | 6 days | Wed 4/21/04 | Wed 4/28/04 | | 0% |
| 41 | Develop organization structure | 1 day | Wed 4/21/04 | Wed 4/21/04 | Project Director | 0% |
| 42 | Develop staffing plan | 1 day | Thu 4/22/04 | Thu 4/22/04 | Project Director | 0% |
| 43 | Obtain resources | 1 day | Fri 4/23/04 | Fri 4/23/04 | Project Director | 0% |
| 44 | Conduct team orientation | 1 day | Wed 4/28/04 | Wed 4/28/04 | Project Director | 0% |
| 45 | Set up standards and procedures for team performance | 1 day | Wed 4/21/04 | Wed 4/21/04 | Team Leader | 0% |
| 46 | Develop Procurement Plans | 4.5 days | Tue 4/13/04 | Mon 4/19/04 | | 0% |
| 47 | Determine procurement requirements | 1 day | Tue 4/13/04 | Wed 4/14/04 | Contracts Manager | 0% |
| 48 | Define subcontractor scope | 1 day | Wed 4/14/04 | Thu 4/15/04 | Contracts Manager | 0% |
| 49 | Identify potential subcontractors | 1 day | Thu 4/15/04 | Fri 4/16/04 | Contracts Manager | 0% |
| 50 | Identify subcontract type | 1 day | Fri 4/16/04 | Mon 4/19/04 | Contracts Manager | 0% |
| 51 | Document subcontractor management plan | 0.5 days | Mon 4/19/04 | Mon 4/19/04 | Contracts Manager,Acceptor | 0% |
| 52 | Set Up Project Environment | 3 days | Thu 4/29/04 | Mon 5/3/04 | | 0% |
| 53 | Prepare facilities | 1 day | Thu 4/29/04 | Thu 4/29/04 | Project Manager | 0% |
| 54 | Set up project standards and procedures | 1 day | Thu 4/29/04 | Thu 4/29/04 | Quality Assurance Manager | 0% |
| 55 | Set up project management tools | 1 day | Fri 4/30/04 | Fri 4/30/04 | Project Manager | 0% |
| 56 | Set up project book | 1 day | Mon 5/3/04 | Mon 5/3/04 | Project Manager | 0% |
| 57 | Document project management plan | 0.5 days | Mon 5/3/04 | Mon 5/3/04 | Project Manager,Acceptor | 0% |
| 58 | Executing | 10 days | Tue 5/4/04 | Mon 5/17/04 | | 0% |
| 59 | Manage Project Data | 9 days | Tue 5/4/04 | Fri 5/14/04 | | 0% |
| 60 | Authorize work | 1 day | Tue 5/4/04 | Tue 5/4/04 | Team Leader | 0% |
| 61 | Manage action items | 1 day | Tue 5/4/04 | Tue 5/4/04 | Project Manager | 0% |
| 62 | Manage project records | 1 day | Fri 5/7/04 | Fri 5/7/04 | Project Manager | 0% |
| 63 | Manage data items | 1 day | Mon 5/10/04 | Mon 5/10/04 | Project Manager | 0% |
| 64 | Manage configuration items | 1 day | Mon 5/10/04 | Mon 5/10/04 | Project Manager | 0% |
| 65 | Manage process data | 1 day | Mon 5/10/04 | Mon 5/10/04 | Project Manager | 0% |
| 66 | Provide general office support | 1 day | Tue 5/11/04 | Tue 5/11/04 | Project Manager | 0% |
| 67 | Administer project security processes | 1 day | Fri 5/14/04 | Fri 5/14/04 | Project Manager | 0% |
| 68 | Manage Project Communication | 5 days | Tue 5/4/04 | Mon 5/10/04 | | 0% |
| 69 | Review progress | 1 day | Tue 5/4/04 | Tue 5/4/04 | Project Director | 0% |
| 70 | Resolve issues | 1 day | Fri 5/7/04 | Fri 5/7/04 | Project Director | 0% |
| 71 | Monitor satisfaction | 1 day | Mon 5/10/04 | Mon 5/10/04 | Project Director | 0% |
| 72 | Manage Team Performance | 7 days | Fri 5/7/04 | Mon 5/17/04 | | 0% |
| 73 | Assign responsibilities | 1 day | Fri 5/7/04 | Fri 5/7/04 | Team Leader | 0% |
| 74 | Meet with team | 1 day | Mon 5/10/04 | Mon 5/10/04 | Team Leader | 0% |
| 75 | Manage team communications | 1 day | Mon 5/17/04 | Mon 5/17/04 | Project Manager | 0% |
| 76 | Recognize success | 1 day | Mon 5/10/04 | Mon 5/10/04 | Project Director | 0% |
| 77 | Monitor team morale | 1 day | Mon 5/17/04 | Mon 5/17/04 | Project Manager | 0% |
| 78 | Conduct team performance reviews | 1 day | Mon 5/10/04 | Mon 5/10/04 | Team Leader | 0% |
| 79 | Provide team training | 1 day | Mon 5/17/04 | Mon 5/17/04 | Project Manager | 0% |
| 80 | Assure Quality | 5 days | Tue 5/4/04 | Mon 5/10/04 | | 0% |
| 81 | Participate in walk-throughs and reviews | 1 day | Tue 5/4/04 | Tue 5/4/04 | Quality Assurance Manager | 0% |
| 82 | Conduct inspections and audits | 1 day | Fri 5/7/04 | Fri 5/7/04 | Quality Assurance Manager | 0% |
| 83 | Participate in testing | 1 day | Mon 5/10/04 | Mon 5/10/04 | Quality Assurance Manager | 0% |
| 84 | Conduct project reviews | 1 day | Mon 5/10/04 | Mon 5/10/04 | Quality Assurance Manager | 0% |
| 85 | Contracting with Subcontractors | 5 days | Tue 5/4/04 | Mon 5/10/04 | | 0% |
| 86 | Issue requisition documents | 1 day | Tue 5/4/04 | Tue 5/4/04 | Contracts Manager | 0% |
| 87 | Evaluate responses | 1 day | Fri 5/7/04 | Fri 5/7/04 | Contracts Manager | 0% |
| 88 | Negotiate subcontractor contract | 1 day | Mon 5/10/04 | Mon 5/10/04 | Contracts Manager | 0% |
| 89 | Manage subcontractor contract | 1 day | Mon 5/10/04 | Mon 5/10/04 | Contracts Manager | 0% |
| 90 | Controlling | 15.5 days | Mon 5/10/04 | Mon 5/31/04 | | 0% |
| 91 | Manage Scope and Requirements | 5 days | Tue 5/18/04 | Mon 5/24/04 | | 0% |
| 92 | Manage scope | 1 day | Tue 5/18/04 | Tue 5/18/04 | Project Manager | 0% |
| 93 | Manage requirements | 1 day | Fri 5/21/04 | Fri 5/21/04 | Project Manager | 0% |
| 94 | Control decisions | 1 day | Mon 5/24/04 | Mon 5/24/04 | Project Manager | 0% |
| 95 | Control changes | 1 day | Mon 5/24/04 | Mon 5/24/04 | Project Manager | 0% |
| 96 | Control Schedule | 5.5 days | Mon 5/24/04 | Mon 5/31/04 | | 0% |
| 97 | Track status | 0.5 days | Mon 5/31/04 | Mon 5/31/04 | Team Leader,Project Manager | 0% |
| 98 | Maintain work plans | 1 day | Mon 5/24/04 | Mon 5/24/04 | Project Manager | 0% |
| 99 | Manage Risks | 1 day | Tue 5/25/04 | Tue 5/25/04 | | 0% |
| 100 | Manage risks | 1 day | Tue 5/25/04 | Tue 5/25/04 | Project Manager | 0% |
| 101 | Manage Finances | 15 days | Mon 5/10/04 | Fri 5/28/04 | | 0% |
| 102 | Monitor cost and schedule variance | 1 day | Fri 5/28/04 | Fri 5/28/04 | Project Manager | 0% |
| 103 | Control costs | 1 day | Mon 5/10/04 | Mon 5/10/04 | Project Director | 0% |
| 104 | Maintain financial plan | 1 day | Tue 5/11/04 | Tue 5/11/04 | Project Director | 0% |
| 105 | Control Quality | 5 days | Mon 5/10/04 | Fri 5/14/04 | | 0% |
| 106 | Control quality | 1 day | Mon 5/10/04 | Mon 5/10/04 | Quality Assurance Manager | 0% |
| 107 | Measure quality levels | 1 day | Tue 5/11/04 | Tue 5/11/04 | Quality Assurance Manager | 0% |
| 108 | Facilitate continuous improvement | 1 day | Fri 5/14/04 | Fri 5/14/04 | Quality Assurance Manager | 0% |
| 109 | Produce Performance Reports | 15.5 days | Mon 5/10/04 | Mon 5/31/04 | | 0% |
| 110 | Report weekly status | 0.5 days | Mon 5/10/04 | Mon 5/10/04 | Team Leader,Acceptor | 0% |
| 111 | Report monthly status | 0.5 days | Mon 5/31/04 | Mon 5/31/04 | Project Manager,Acceptor | 0% |
| 112 | Closing | 6.5 days | Mon 5/31/04 | Tue 6/8/04 | | 0% |
| 113 | Manage Project Close | 6.5 days | Mon 5/31/04 | Tue 6/8/04 | | 0% |
| 114 | Manage project acceptance | 0.5 days | Mon 5/31/04 | Mon 5/31/04 | Project Manager,Acceptor | 0% |
| 115 | Assess satisfaction | 1 day | Tue 6/1/04 | Tue 6/1/04 | Project Manager | 0% |
| 116 | Summarize project results and lessons learned | 1 day | Wed 6/2/04 | Wed 6/2/04 | Project Manager | 0% |
| 117 | Review and recognize team performance | 1 day | Thu 6/3/04 | Thu 6/3/04 | Project Manager | 0% |
| 118 | Review and reconcile financial performance | 1 day | Mon 6/7/04 | Mon 6/7/04 | Project Manager | 0% |
| 119 | Close the project records | 1 day | Tue 6/8/04 | Tue 6/8/04 | Project Manager | 0% |